New Work and Remodeling on Schedule at BPSD

The Bartlesville Public School District's year get underway one month from Monday on August 13th. Community Relations Coordinator Jamye Ryan is reporting that demolition at Central Middle School is already 80% complete after only a few weeks of work. The interior walls have come down at Madison Middle School and new walls are already up around the building.
At the High School, the interior of the second floor addition is complete, with 90% of the first floor addition complete. The new Science wing at the High School is also nearly done. Grounds crews are expected to start moving furniture to the second floor during the week of July 20th. It's expected that students at all BPSD schools will begin the 2015-2016 school year on time.